In October of 2026, JR&B Completed a small patch project at specific systems. Over the course of three days a crew of four was able to break up over two thousand square feet of six inch paving that had collapsed. They were then able to fix the subgrade soil compaction issue that led to the cracks in the first place and repour the sections eight inches thick. 

This project was promarily done by abitsae’s crew and used our mini excavator, skid steer, and out drop hammer breaking attachment. All dry material was hauled out by JR&B Dump trucks and Dolese Concrete was pivitol in delivering the necessary concrete right on schedule. This project used one bundle of half inch rebar, approximately equivilent to three thousand line feet of steel. All tied by hand. Check our social media pages below to for a video recap of the whole project!